Baseline reflects current best estimates. Move sliders to explore scenarios.
BIC arrival
End of August
Range: 15 Jul → 30 Nov. Independent of ACPR.
Conditional Licence
Mid-September
Range: 15 Jul → 15 Nov. ACPR-driven.
Lifting delta
+2 weeks
Weeks Conditional → Lifting (= Bank Code).
Card order placed
Mid-September
Range: 15 Jul → 12 Oct. Production = 8 weeks.
Internal testing in prod
4 weeks
Weeks employee-only before public launch.